top of page

LAUNCH Work Plan

  • Amber Freeman
  • Jun 23, 2016
  • 2 min read

Timeline for my project until August...

Week 4 (July 5–8)

Goal 1: Set up the Raspberry Pi.

Goal 2: Wire the Sensors

Goal 3: Successful testing of the sensors with simple python programs

Monday – Pi Set up-hardware/software, Raspian, Global Clock

Tuesday – Pi Set up-file organization, Start wiring breadboard (Temp/Humidity, UV, Motion, Camera)

Wednesday – Wiring continued

Thursday – Python programs

Friday – Sensor testing

Date/Time for Conference with Mentor ________________

Date/Time to Email Progress to Mentor ________________

Week 5 (July 11-15)

Goal 1: Wiring peripherals

Goal 2: Successful test of peripherals

Goal 3:Code for temp/humidity sensor finished

Monday – Wire lights/test

Tuesday – Wire Mist King/test

Wednesday – Python code for temp/humidity

Thursday – Test code to files/localhost web server

Friday – Python code for motion sensor/camera

Date/Time for Conference with Mentor ________________

Date/Time to Email Progress to Mentor ________________

Week 6: (July 18-22)

Goal 1: Code for motion/camera sensors finished

Goal 2: UV sensor finished

Goal 3:Successful test - full functionality in 1 hour increment

Monday – Python code for motion sensor/camera/Test code to files/localhost web server

Tuesday – Python code for UV sensor

Wednesday – Test code to files/localhost web server

Thursday – Full functionality testing

Friday – Full functionality testing

Date/Time for Conference with Mentor ________________

Date/Time to Email Progress to Mentor ________________

Week 7: (July 25-29)

Goal 1: Web server built

Goal 2: Web Site built

Goal 3:

Monday – Build Web Server

Tuesday – Build Web Server

Wednesday – Test full data to Web Server

Thursday – Build Web Site

Friday – Load HTML into python program

Date/Time for Conference with Mentor ________________

Date/Time to Email Progress to Mentor ________________

Week 8: (August 1-5)

Goal 1: Build email/text alert system

Goal 2: Build System Container

Goal 3:Maybe Smart phone app?

Monday – Text/alert system

Tuesday – Text/alert system

Wednesday – Build container for Pi, circuitry, and sensors

Thursday – Mount container on cage

Friday – Mobile app capability?

Date/Time for Conference with Mentor ________________

Date/Time to Email Progress to Mentor ________________

Week 9: (August 8-12)

Goal 1: Finish Presentation

Goal 2: Finish Poster

Goal 3: Project Wrap Up

Monday – Info gather, lit review

Tuesday – Info gather, lit review

Wednesday – Finish Presentation

Thursday – Finish Presentation/Poster

Friday – Finish Poster

Date/Time for Conference with Mentor ________________

Date/Time to Email Progress to Mentor ________________

Week 10: (August 15-19)

Goal 1: Complete PowerPoint Presentation

Goal 2: Complete Poster Presentation

Goal 3: Project Completion

Monday - Conference with Mentor Time:_______________

Tuesday -

Wednesday - Upload Project report to SKC Moodle

Upload PowerPoint and poster to SKC Moodle

Thursday – Webinar Presentations

Friday – Final Project report due, upload to SKC Moodle;

Upload final PowerPoint and poster to SKC Moodle


 
 
 